Reading: The Ambassador Bridge has lost its spot as the busiest U.S.-Canada trade corridor
Share
Today in CanadaToday in Canada
Font ResizerAa
  • News
  • Things To Do
  • Lifestyle
  • Entertainment
  • Health
  • Travel
Search
  • Home
  • News
  • Lifestyle
  • Things To Do
  • Entertainment
  • Health
  • Tech
  • Travel
  • Press Release
  • Spotlight
Have an existing account? Sign In
Follow US
Today in Canada > News > The Ambassador Bridge has lost its spot as the busiest U.S.-Canada trade corridor
News

The Ambassador Bridge has lost its spot as the busiest U.S.-Canada trade corridor

Press Room
Last updated: 2026/04/07 at 7:56 AM
Press Room Published April 7, 2026
Share
The Ambassador Bridge has lost its spot as the busiest U.S.-Canada trade corridor
SHARE

Listen to this article

Estimated 5 minutes

The audio version of this article is generated by AI-based technology. Mispronunciations can occur. We are working with our partners to continually review and improve the results.

Canada’s busiest trade corridor has quietly moved north.

High tolls at the Ambassador Bridge have driven record commercial traffic through the Blue Water Bridge, allowing the Sarnia, Ont., crossing to overtake Windsor as the busiest commercial crossing on the Canada-U.S. border for the first time in decades.

“The Blue Water Bridge has surpassed all other international crossings in commercial traffic volume,” Alexandre Gauthier, the communications manager for the Federal Bridge Corporation Limited (FBCL) said in an email to CBC News.

FBCL is a Crown Corporation that owns and operates certain border crossings, including the Blue Water Bridge.

For every month in 2025, the Blue Water Bridge surpassed the Ambassador Bridge, with about 2.1 million commercial truck trips at Sarnia that year compared to roughly 1.9 million at Windsor, according to data from the Bridge and Tunnel Operators Association.

The trend has continued into 2026. In the first three months of the year, the Ambassador Bridge saw 496,796 commercial truck trips, compared with 531,732 at the Blue Water Bridge.

Tolls reshape routes

Tolls for commercial trucks at the Ambassador Bridge are the highest in the region — up to $27 per axle — almost four times the $7 per axle at Blue Water Bridge and the proposed $12 an axle rate for Gordie Howe, when it finally opens.

The toll gap has effectively redirected continental supply chains north to Sarnia, reshaping one of North America’s busiest trade corridors and arriving as another complication for the Gordie Howe bridge, already late and over budget.

“Price sensitivity entered in the market for the supply chain,” Stephen Laskowski, the President and CEO of the Canadian Trucking Alliance and the Ontario Trucking Association told CBC News.

man in suit on parliament hill
Stephen Laskowski, president of the Canadian Trucking Alliance, is pictured on Parliament Hill in Ottawa in 2023. (Robyn Miller/CBC)

Laskowski said the result is a rare moment of distortion at one of North America’s most critical trade chokepoints.

“Historically over the decades, the Ambassador Bridge was always the leading crossing between Michigan and Ontario by a significant number,” he said.

“It goes to show you the price sensitivity of tolls and the tremendous value of the Gordie Howe Bridge to the supply chain.”

Relief still delayed

There is still no firm open date for the Gordie Howe International Bridge — meant to modernize and decongest the Windsor-Detroit corridor — the opening of which has been delayed twice and is still politically and administratively uncertain. Last month, the company said it would open “this spring.”

Bridge in the background with Windsor Salt building in the front. Taken from a drone
A view of the Gordie Howe International Bridge under construction in April 2025. (Jacob Barker/CBC)

Those delays are not trivial: one recent American analysis estimated losses of up to $7 million US per week tied to a postponed launch.

The mega-project, hailed as a “once-in-generation undertaking,” is also about $700 million over its $5.4 billion budget, pushing the cost to roughly $6.1 billion, despite early federal assurances back in 2015 that the public-private-partnership, or P3 model, would keep it “on time and on budget.”

Promise vs. reality

“Politicians loved it,” Matti Siemiatycki, a professor of geography and urban planning at the University of Toronto whose work focuses on large-scale infrastructure projects said of the P3 model. “They clung to this idea of ‘on time and on budget’ like a life raft.”

A man stands near a transit turnstile.
Matti Siemiatycki, a professor of geography and urban planning at the University of Toronto is pictured at a subway station in Toronto in 2025. (Chris Glover/CBC News)

The P3 became the dominant way governments across Canada tried to build infrastructure for a decade between the early 2000s and the early 2010s, but they eventually fell out of favour, Semiatycki said, because the promise of “on time and on budget” didn’t consistently hold.

They’ve recently seen a resurgence, Semiatycki said, especially when it comes to major transit project, but recently, as they did more than a decade ago, “the P3 has proven to be adverserial.”

Instead of working together, he said, the private and public sector end up fighting over who pays, in the end, governments still end up paying when things go wrong.

“There’s transferring risk on paper, but in practice you have to wonder who’s responsible for these risks,” he said. He noted some risks can’t actually be shifted, such as the COVID-19 pandemic and threats from U.S. President Donald Trump — so when they hit, governments must step in to keep the project moving.

U.S. President Donald Trump, who previously threatened to block the Gordie Howe International Bridge, is pictured during a public appearance in 2017. (Joshua Roberts/Reuters)

“No one takes on risk for free,” he said. “The companies will charge a premium for that risk and what we’re seeing is that when risks materialize, oftentimes governments still end up stepping in and paying.”

CBC News asked Infrastructure Canada and the Windsor-Detroit Bridge Authority, the consortium responsible for the Gordie Howe International Bridge about the project’s delays, rising costs and how risk is being shared but did not receive a response by deadline.

The Ambassador Bridge was also asked about rising tolls and shifting traffic patterns but did not respond.

Quick Link

  • Stars
  • Screen
  • Culture
  • Media
  • Videos
Share This Article
Facebook Twitter Email Print
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

You Might Also Like

House prices dropping in Canada’s most expensive cities, but still out of reach for many
News

House prices dropping in Canada’s most expensive cities, but still out of reach for many

April 7, 2026
How Canadian military members violated intelligence-gathering rules during COVID-19
News

How Canadian military members violated intelligence-gathering rules during COVID-19

April 7, 2026
Watchdog’s report on controversial RCMP unit delayed due to lack of chairperson
News

Watchdog’s report on controversial RCMP unit delayed due to lack of chairperson

April 7, 2026
Still have to file your taxes? Here’s how to find yourself some money
News

Still have to file your taxes? Here’s how to find yourself some money

April 7, 2026
© 2023 Today in Canada. All Rights Reserved.
  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact
Welcome Back!

Sign in to your account

Lost your password?