Reading: Via Rail pays out $31M in travel vouchers because of delays
Share
Today in CanadaToday in Canada
Font ResizerAa
  • News
  • Things To Do
  • Lifestyle
  • Entertainment
  • Health
  • Travel
Search
  • Home
  • News
  • Lifestyle
  • Things To Do
  • Entertainment
  • Health
  • Tech
  • Travel
  • Press Release
  • Spotlight
Have an existing account? Sign In
Follow US
Today in Canada > News > Via Rail pays out $31M in travel vouchers because of delays
News

Via Rail pays out $31M in travel vouchers because of delays

Press Room
Last updated: 2025/10/08 at 4:31 AM
Press Room Published October 8, 2025
Share
SHARE

Via Rail has offered $31 million in travel vouchers to hundreds of thousands of passengers whose trains were more than one hour late since last fall, mostly as a result of new speed limits at rail crossings on CN tracks.

Travel vouchers worth 50 per cent of fares are offered to passengers whenever a train is delayed by more than an hour on the Quebec City-Windsor corridor, the busiest stretch in Via’s system. The value goes up to 100 per cent when the delay exceeds four hours.

The $31-million figure is equivalent to seven per cent of the Crown corporation’s total revenues in 2024, illustrating the extent of the problems experienced by passengers who have suffered record delays since the start of a conflict with CN during last year’s Thanksgiving weekend.

“This is not good news for anyone. As taxpayers, we can’t be happy to have to pay penalties like these, and it is even worse for users,” said Jacques Roy, a retired professor who specialized in logistics at HEC Montréal.

“This is really a reflection of bad service.”

CN imposed speed restrictions a year ago at all rail crossings used by Via, arguing its new trains might not be long or heavy enough to activate security measures every single time.

WATCH | Why the trains don’t run on time:

Prior to the conflict, in August 2024, 45 per cent of Via trains along that corridor were on time, but by this August it had dropped to 29 per cent.

“It’s a significant drop,” said Roy. “It’s a bit discouraging for users who already suffer from a lack of reliability.”

Via considers its trains on that corridor to be on time when they come in within 10 or 15 minutes of their planned arrival.

Since the start of the conflict, however, Via has calculated that about 15 per cent of its trains on that corridor were at least one hour late.

Transport Minister Steven MacKinnon says Via’s performance is unacceptable, and is hurting both passengers and its business strategy.

“This is obviously sub-optimal and we will have to focus very squarely on improving those results,” he said in an interview.

WATCH | Historic delays on busy corridor:

Via Rail, CN point fingers as late arrivals hit new high

Tardiness is nothing new at Via Rail, but late arrivals are reaching historic levels between Quebec City and Windsor as passenger trains have been forced to slow down at hundreds of rail crossings operated by CN Rail.

The dispute between CN and Via is related to the number of axles on the latter’s new Venture trains, in use since 2022.

When Via runs a train composed of one locomotive and five cars, there are only 24 axles, short of the 32 axles called for by CN to ensure that barriers and signals are activated at rail crossings.

When a train nears a crossing, an electrical signal triggers those safety warnings — but the signal depends on the length and weight of the train.

So CN imposed speed limits for Via trains at level crossings.

Instead of a maximum cruising speed of 160 km/h, engineers often slowed to below 80 km/h at crossings to confirm that the safety features were activated, instead of relying on automated systems.

After seeing passenger trains hit record delays in recent months, Via struck a stopgap deal with CN in August — allowing trains to roll at a constant, albeit reduced, speed over longer segments, without having to confirm the automatic activation of safety systems.

“This new approach simplifies operations and offers the potential to reduce delays and improve reliability for passengers, but it is still too early to confirm the impact on our on-time performance,” said Via spokesperson Karl Helou.

The first signs are encouraging, but Helou says it’s too early to say that problems have been resolved.

“This is a step forward, but not a definitive solution,” he said.

CN says the new speed limits ensure that the safety features at rail crossings are turned on quickly enough.

But the dispute is still before Quebec’s Superior Court, which in April rejected Via’s request for an injunction removing the original restrictions.

The federal Ministry of Transport is also seeking an agreement between the two parties, although the departure from cabinet of then-minister Chrystia Freeland created additional delays.

Both Via and CN insist they will not compromise on safety, but cannot agree on the extent of the problem at level crossings and the measures needed to protect all passengers.

Quick Link

  • Stars
  • Screen
  • Culture
  • Media
  • Videos
Share This Article
Facebook Twitter Email Print
What do you think?
Love0
Sad0
Happy0
Sleepy0
Angry0
Dead0
Wink0
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

You Might Also Like

News

Syilx Okanagan Nation chiefs deny issuing cease and desist letter in ostrich cull controversy

October 10, 2025
News

Vancouver Park Board’s apology over Harry Potter event catches J.K. Rowling’s attention

October 10, 2025
News

Nuclear operator found not criminally responsible for leaking power plant vulnerabilities on YouTube

October 10, 2025
News

Majority of Canadians — including B.C. residents — support Alberta’s pipeline push, poll finds

October 10, 2025
© 2023 Today in Canada. All Rights Reserved.
  • Privacy Policy
  • Terms of use
  • Advertise
  • Contact
Welcome Back!

Sign in to your account

Lost your password?